基于并行工程的客滚船设计工期优化研究

杜尊峰1, 樊涛1, 赵勇2, 文树吉1   

  1. 1.天津大学 建筑工程学院 水利工程仿真与安全国家重点实验室 天津 300354;
    2.招商局邮轮研究院(上海)有限公司 上海 200137
  • 收稿日期:2022-09-19 修回日期:2022-11-03 出版日期:2023-04-25 发布日期:2023-04-27
  • 作者简介:杜尊峰(1984-),男,博士,副教授。研究方向:船舶与海洋装备智能设计及工程管理。樊涛(1999-),男,硕士研究生。研究方向:船舶与海洋装备智能设计及工程管理。赵勇(1984-),男,本科,工程师。研究方向:船舶结构设计与管理。文树吉(1997-),男,硕士研究生。研究方向:船舶与海洋装备智能设计及工程管理。
  • 基金资助:
    天津市交通运输科技发展计划项目(2022-48)

Schedule Optimization of Ro-Ro Passenger Ship Design Based on Concurrent Engineering

DU Zunfeng1, FAN Tao1, ZHAO Yong2, WEN Shuji1   

  1. 1. State Key Lab of Hydraulic Engineering Simulation and Safety, School of Civil Engineering, Tianjin University, Tianjin 300354, China;
    2. China Merchants Cruise Research Institute (Shanghai) Co., Ltd., Shanghai 200137, China
  • Received:2022-09-19 Revised:2022-11-03 Online:2023-04-25 Published:2023-04-27

摘要: 传统以二维图纸为主的串行设计模式在客滚船的设计中存在诸多缺陷,已无法适应目前客滚船的技术发展需求。该文分析传统客滚船设计流程,针对其存在的问题,以基于模型定义技术为支撑,应用并行工程理论对客滚船设计周期进行优化。通过结构专业3D一体化设计与舾装专业提前设计的并行设计模式,实现初步设计、详细设计以及生产设计协同进行。文中以设计结构矩阵为基本的计算工具,通过某客滚船的实际设计,对比优化前后客滚船设计工期的变化,验证理论的可行性及有效性。结果表明:应用并行工程后,能够有效降低客滚船设计工作量,解决结构与舾装专业设计不协调问题,缩短客滚船设计工期,工期优化率达25.7%。

关键词: 客滚船, 并行设计模式, 设计结构矩阵, 工期优化

Abstract: The traditional serial design mode based on two-dimensional drawings has many defects in the design of ro-ro passenger ships, which cannot meet the development needs of ro-ro passenger ships. In view of the problems in the traditional design process of the ro-ro passenger ship, the design schedule of the ro-ro passenger ship is optimized by applying concurrent engineering theory with the support of the model based definition(MBD) technology. The preliminary design, detailed design and production design are coordinated through the concurrent design of the 3D integrated structural design and the advance outfitting design. The design structure matrix is used as a basic calculation tool to compare the changes in the design period of the ro-ro passenger ship before and after optimization based on the design of a ro-ro passenger ship, in order to verify the feasibility and validity of the theory. The results show that the application of the concurrent engineering can effectively reduce the design workload of the ro-ro passenger, and solve the incoordination between the professional structural design and outfitting design, as well as shorten the design duration of the ro-ro passenger ship, with a schedule optimization rate of 25.7%.

Key words: ro-ro passenger ship, concurrent design mode, design structure matrix, schedule optimization