海洋修井机泥浆系统优化

孟庆元, 孙强, 韩鹏   

  1. 中海油能源发展装备技术有限公司 天津300452
  • 收稿日期:2021-02-21 修回日期:2021-03-31 出版日期:2021-12-25 发布日期:2022-01-07
  • 作者简介:孟庆元(1987-),男,硕士,工程师。研究方向:海洋钻修机设计。孙 强(1988-),男,本科,工程师。研究方向:海洋钻修机设计。韩 鹏(1990-),男,本科,工程师。研究方向:海洋钻修机设计。

Optimization of Mud System for Offshore Workover Rig

MENG Qingyuan, SUN Qiang, HAN Peng   

  1. CNOOC EnerTech Equipment Technology Co., Ltd., Tianjin 300452,China
  • Received:2021-02-21 Revised:2021-03-31 Online:2021-12-25 Published:2022-01-07

摘要: 石油是日常生活、工业生产、航天军工无可替代的能源,同时作为一种不可再生能源,它的开发与利用非常重要。为了保持稳定的产量,在开发新油田的同时,也要充分利用现有油田的资源。所以利用修井机来修护、保养现有井口尤为重要。修井的重要媒介是修井液(主要组成成分为泥浆),修井液的循环是否顺畅、配比(配浆)是否正确关系着修井作业能否顺利进行。该文研究了近几年修井机项目的工艺流程及设备布置方案,选取某一典型项目中出现的问题进行案例分析,从而得出结论:在修井液循环和配浆过程中,由于泥浆罐的布置顺序不同、泥浆罐与高压泥浆泵的相对位置不同,对实际建造和功能的实现有重要影响,甚至由于无法合理布置管线导致工艺流程无法实现;最终根据存在的问题提出两套优化方案,供以后的修井机项目参考借鉴。

关键词: 修井机, 修井液, 修井液循环, 配浆, 工艺流程

Abstract: Petroleum is the irreplaceable energy source in daily life, industrial production, aerospace and military industry. As a non-renewable energy source, the development and utilization of petroleum are very important. While exploiting new oilfields, the resources of the current oilfields should be fully utilized to maintain stable production. It is therefore particularly important to use workover rigs to repair and maintain the existing wellheads. The important medium of workover is the workover fluid, which is mainly composed of mud. The success of the workover operation is related to the smooth circulation and the correct proportion (slurry preparation) of the workover fluid. The technological process and the equipment layout scheme of the workover rig projects in the recent years are researched to select the problems in the typical project for the case analysis. It is concluded that in the process of the workover fluid circulation and the slurry preparation, the different arrangement sequence of the mud tanks and the different relative positions of the mud tank and the high-pressure mud pump have the important impact on the actual construction and function realization, even resulting in the failure of the technological process due to the unreasonable arrangement of pipelines. Finally, two sets of optimization schemes are proposed based on the existing problems to provide reference in the future projects of the workover rig.

Key words: workover rig, workover fluid, workover fluid circulation, slurry preparation, technological process